A bill of quantities turns a loosely defined renovation into a list of work that several contractors can price on the same basis. It does not replace a design, a site inspection or a contract, yet it leaves far less room for conflicting assumptions about demolition, repairs, materials, finishes and exclusions. In an older Lisbon flat, where opening a wall or floor may reveal surprises, it also separates what is defined from what still needs confirmation on site.

Contents

  1. What should a bill of quantities include?
  2. Start with the decisions already made
  3. How to measure without creating false precision
  4. Ask for unit rates and stated exclusions
  5. Connect the bill to the programme and procurement
  6. How to use the bill during construction

What should a bill of quantities include?

A bill of quantities is arranged in work sections, with clear descriptions, units and quantities. Instead of requesting a “bathroom renovation”, list the operations needed to produce the same result: protection to access routes, demolition, removal, levelling, waterproofing, finishes, water and drainage work, electrics, sanitaryware, painting, cleaning and reinstatement.

A useful line answers four questions: what is done, where it is done, how it is measured and what is included. For example: “supply and installation of ceramic wall finish in sanitary area, including substrate preparation, cuts, adhesives, grout and finishing trims; m²”. Avoid lines such as “miscellaneous materials” or “complete finishes”: they hide differences that emerge only once the work is under way.

Where drawings exist, the bill should identify them by date and revision. Lisbon City Council explains that specialist designs contain technical specifications for building systems and equipment; that information should reach the bill rather than remain scattered across PDFs and messages. Read Lisbon City Council’s guidance on specialist designs.

Start with the decisions already made

There is little value in measuring every item before the main choices are settled. First confirm the layout, door swing directions, kitchen equipment positions, water points, ventilation approach and finishes that change floor or wall build-ups. Then match each decision to a line or note in the bill.

  1. Gather dimensioned plans, photographs and available detail drawings.
  2. Mark what is existing, what stays and what will be removed.
  3. List selected products by brand, reference or minimum performance.
  4. Flag outstanding decisions instead of presenting them as settled.

There is an important difference between an estimated quantity and an undecided choice. If the tap has not been selected, state whether the price includes installation only or supply as well, and set a transparent range or allowance. For the latter, see how to manage provisional allowances in a renovation without turning them into a catch-all for unforeseen costs.

How to measure without creating false precision

Measure floor and wall finish areas, linear metres of skirting, cornices, pipework or cabinetry, and units for doors, appliances, sockets and light fittings. Record the method: gross or net area, height allowed for, whether openings are deducted, and whether each item includes supply, installation, delivery and waste.

There is little sense in using two decimal places for an old wall whose condition will only be known after finishes are removed. In those cases, write a reference quantity and a clear note: “localised substrate repair to be confirmed after demolition; work only after written approval”. This lets you compare quoted unit rates without pretending an unknown condition has a fixed price.

Always separate preparatory work and finishing details. Two kitchen quotes can show the same floor area, while only one includes levelling, door-jamb cuts, thresholds and sealant. Those small items are often where disputes arise at the end.

Example lines that prevent misleading comparisons
SectionMeasurementScope note
New flooringm²State whether levelling, skirting, joints and trims are included.
Wall paintingm²Separate preparation, primer, coats and crack repairs.
Sockets and switchesunitState fittings, back box, circuit and applicable testing.
Kitchen cabinetrylinear m or unitSeparate carcasses, fronts, worktop, hardware and installation.
Renovation interior with technical drawings and measuring tools prepared for site coordination.

Ask for unit rates and stated exclusions

The total price matters, but it is not enough. Request a unit rate for every line, a subtotal for each section, VAT shown separately and a quotation validity period. If something changes, you can understand the cost of adding, omitting or substituting an item instead of negotiating from memory.

Exclusions should sit in their own section. Frequent examples include municipal fees, design services, public-space occupation, structural repairs found after opening up, condominium work, appliance supply, gas connection, or reinstatement of elements not identified during the visit. An exclusion is not a mistake; it becomes one when it appears only after appointment.

For private works above the applicable legal threshold, the contract must be in writing. IMPIC states that the minimum content includes the parties and their qualifications, the contract object — including written and drawn documents where they exist — value, programme and payment terms. A dated, signed bill attached to the contract gives that object a checkable form. See IMPIC’s information on private construction contracts.

Connect the bill to the programme and procurement

A bill of quantities is not only a pricing tool. Once each significant section has a decision date, order date and installation date, it exposes dependencies that regularly stop work: a worktop depends on final cabinet measurements; cabinets depend on service positions; wall finishes depend on waterproofing and levelling.

Add a simple column to relevant lines: “client decision”, “order”, “delivery to site” and “installation”. Do not schedule delivery for the day the product is needed. In an apartment building, confirm delivery hours, lift protection, carrying route and storage location first. Our guide to site induction for an apartment renovation helps turn those rules into practical decisions before the first delivery arrives.

Where work is subject to prior communication, Lisbon City Council states that architectural and specialist designs must be submitted together, alongside other documents required to carry out the work. The bill should therefore distinguish routine internal items from work dependent on those documents and on any public-space occupation. Read Lisbon City Council’s requirements for building works under prior communication.

How to use the bill during construction

At appointment, freeze one version: date, revision, related drawings, exclusions, unit rates and total. Every later change should identify the affected line and state its cost and time effect before the work is carried out. A photograph or message can explain why, but it does not replace an approval that states what has changed.

At site meetings, review only four groups: completed and measured work, work requiring confirmation before it is covered, materials with pending orders, and requested changes. For payments, connect each certificate or invoice to sections that have actually been completed, rather than to a generic percentage of the overall quote.

There is a sensible boundary to homeowner control. Do not change structural, electrical, gas, waterproofing or ventilation solutions from a bill line alone. When the existing building conflicts with the design, stop that workfront and seek confirmation from the responsible designer or trade professional. A good document does not remove technical decisions; it makes clear when they are required.

Key takeaways

  • Build one section per system and describe each line with a unit, clear inclusion and clear limit.
  • Request unit rates, exclusions and dated revisions; a total alone cannot be properly compared or adjusted.
  • Use estimated quantities only where opening up may reveal unknown site conditions.
  • Link decisions and orders to bill lines before booking trades and deliveries.

Before requesting quotes, gather the plan, photographs, confirmed selections and an honest list of open decisions. If you need to turn that material into a coordinated scope for a Lisbon renovation, contact Obra Lisboa with the rooms involved, the property’s current condition and your intended start date.

Sources and further reading

Editorial image; it does not depict an Obra Lisboa project.

Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
ObraLisboa - Construção e Remodelação de propriedades
let's create
together