September 2026 construction costs: update a renovation quote before appointing

Structural Work
·
Joinery
·
Decoration
·
Consultancy
·
3D Design
·
Interior Design
·
Construction
·
Full Renovations
·
Architecture
·
Engineering
·
Demolition
·
Painting and Finishes
·
Electrical and Plumbing
·
Wall and Floor Finishes
Renovation planning table in Lisbon with drawings, material samples and a work list.

If you received a renovation quote weeks or months ago, ask for a written update before appointing the contractor. In September 2026, new-housing construction costs rose 7.4% year on year; materials rose 7.2% and labour 7.7%. These figures do not replace the quote for your particular project, but they make it risky to treat an older proposal as a guaranteed price and programme. The useful decision is to confirm what remains valid, what still needs measuring and which purchases need to be settled first.

Contents

  1. What changed in costs, and why it matters for a renovation
  2. Can an older quote still be used to appoint a contractor?
  3. Split the price into blocks you can verify
  4. Do not confuse a public index with automatic contract adjustment
  5. Which purchases should be decided before work starts
  6. How to appoint without losing control

What changed in costs, and why it matters for a renovation

Statistics Portugal published the September figures on 9 November 2026: the New Housing Construction Cost Index rose 7.4% year on year. Labour increased slightly more than materials: 7.7% against 7.2%.

An apartment renovation is not a new home and should not receive an automatic 7.4% uplift. It does, however, rely on the same sensitive elements: specialist trades, finishes, windows, bespoke kitchens, electrical equipment and waiting time between work stages. A quote prepared before decisions such as retaining or replacing pipework, levelling a floor or moving a kitchen may no longer match the work you intend to carry out.

Use the index as a prompt to review the quote, not as a formula for blindly accepting a rise or demanding a reduction. To follow statistical releases and check the period behind each figure, see the Statistics Portugal website.

Can an older quote still be used to appoint a contractor?

It can be a sound starting point if it states a date, scope, quantities, exclusions and a validity period. Without these elements, it may only show a broad order of cost.

Before appointment, send the contractor a short list of confirmations:

  1. Which works, materials and quantities are included today?
  2. Which prices depend on supplier confirmation, stock or final measurement?
  3. Which items remain provisional, estimated or undecided?
  4. What is the first realistic start date and planned sequence?
  5. Which client changes could affect cost or timing?

Ask for the answer in an identified revision of the quote. An informal message exchange does not adequately establish whether demolition, common-area protection, waste removal, plaster repairs, final cleaning or final connections are included. Also confirm whether the stated programme starts at appointment, material delivery or actual access to the flat.

Split the price into blocks you can verify

A useful update does not need to turn the quote into an endless document. It should separate items already settled from items that still depend on a choice or site verification.

Look for at least four blocks: enabling works and demolition; services and concealed work; finishes; and client-selected supplies. This makes it easier to see which part of the price and programme changes if you replace flooring or postpone a kitchen.

It is also the best way to avoid comparing two quotes with the same total but different contents. To organise questions between trades, keep a renovation clarification log with the question, decision, responsible person and deadline. A decision without a date tends to return when a team is already waiting.

A practical way to read an updated quote
BlockWhat to confirmRisk when left vague
Demolition and preparationProtection, removal, levelling and foreseeable discoveriesExtra work at the very beginning
ServicesWater points, electrical work, ventilation and technical accessWalls reopened and delays
FinishesBrand, model, format, application and trimsSubstitutions with no quality comparison
SuppliesLead time, installation and responsibility for measurementA work stage stopped while materials are awaited
Apartment interior under renovation with organised materials and protected areas before finishes are installed.

Do not confuse a public index with automatic contract adjustment

Official indices are useful for understanding cost movements and for certain contract price-review mechanisms. IMPIC publishes construction price-review indices in Diário da República, including references to labour, materials and support equipment.

For a private renovation, the applicable position depends on the contract and its agreed wording. Do not assume that a generic reference to rising prices permits any amount to change; equally, do not assume the price remains open-ended when the quotation has expired, the scope has changed or key choices are still unresolved.

If a price-review clause is proposed, ask it to identify the covered work, base date, formula or index, evidence required and calculation point. For a short project, early confirmation of critical materials can sometimes be clearer than a clause that is difficult to apply and impossible to check while work is under way.

Which purchases should be decided before work starts

Do not bring every purchase forward simply through fear of price rises. Bring forward decisions that hold up measurement, ordering or installation: windows, shower trays, kitchen furniture, built-in appliances, special finishes, made-to-measure doors and air-conditioning equipment.

Always confirm four points before payment: final measurement, exact reference, supplier lead time and delivery location. An item shown as available in a shop may not be available in the required quantity, finish or size. If delivery must use a lift, narrow staircase or shared area, check packaging, access times and storage conditions as well.

Where the client supplies items, record who measures, who orders, where materials will be stored, who checks for delivery damage and who is responsible if an item does not fit. Organised procurement prevents a seemingly small component from stopping several trades.

How to appoint without losing control

Before the deposit is paid, bring together the final quote, drawing or decision list, staged programme and payment conditions. Payments should follow verifiable work, materials genuinely ordered where justified, and clear delivery milestones.

Also define who decides each alteration and by when. A renovation responsibility matrix helps distinguish who proposes, confirms, approves the cost and provides access to the property. This is particularly useful where an owner, tenant, condominium, designer and several suppliers are involved.

Keep a contingency for technical unknowns, but do not use it to cover foreseeable omissions. If the quote does not state how it will deal with uncovered cracks, out-of-square walls, deteriorated pipework or substrate repairs, ask for criteria and unit rates before work begins.

In the days before the start, also confirm the water, electricity and gas isolation points. A simple utility shut-off plan reduces downtime and limits damage when an existing installation needs work.

Higher costs call for preparation rather than haste: settle the scope you know, keep uncertainty visible and do not sign a programme that ignores decisions, deliveries and access to the building.

Key takeaways

  • Request a dated revision of the quote before appointing a contractor for work that has been on hold.
  • Separate fixed work, provisional items and client-selected supplies.
  • Do not apply an INE percentage directly to your quote; check the contract, scope and actual prices.
  • Decide early on items that control measurement, ordering and the construction sequence.

If you are preparing a renovation in Lisbon, Obra Lisboa can help turn decisions already made into a clear work scope for requesting and comparing quotations. A practical next step is to gather drawings, photographs, priorities and the latest quote before requesting a project review.

Sources and further reading

Editorial image; it does not depict an Obra Lisboa project.

Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
Let's Work Together
·
ObraLisboa - Construção e Remodelação de propriedades
let's create
together