
A clarification log turns site questions into decisions with an owner, deadline and written evidence. In a flat renovation, a seemingly minor issue — mirror height, door swing, trap type or socket position — can stop an entire work stage when it exists only in a phone call or site conversation. Set up this document before work starts and update it at every site meeting.
Contents
It is one list of questions that still need an answer for the works to proceed properly. In construction it may be called a request-for-information register; for a home renovation, it does not need formal language or expensive software. A shared spreadsheet, a numbered PDF or a table within the digital project folder is enough, provided everybody uses the same version.
Its purpose is to distinguish three matters that are often mixed together: a technical query, a client choice and a change to the contracted scope. Checking whether a wall can support wall-hung furniture is a technical query; choosing black or stainless-steel handles is a client choice; changing an already ordered worktop for one with different dimensions may affect cost, timing and installation.
For works subject to a licence or prior communication, the site book must record relevant events during execution and remain available on site under Portuguese Ordinance no. 1268/2008 on the site book. Your internal log does not replace it. It complements it by resolving decisions before they become a site problem.
Use one row for each issue and assign a reference number that never changes. Avoid vague labels such as “bathroom” or “check kitchen”. Write the question so that someone absent from the meeting can understand and answer it.
| Status | What it means | Next action |
|---|---|---|
| Open | The question has been logged but has no answer yet. | Assign an owner and deadline. |
| Under review | Information or alternatives still need checking. | Attach a drawing, sample or price. |
| Decided | There is a written approved answer. | Notify the affected team. |
| Completed | The solution has been installed and checked. | File photographic or measurement evidence. |
Log it whenever the decision affects something that will be concealed, made to order or difficult to undo: pipework, cables, waterproofing, wall reinforcement, finished-floor levels, door openings and bespoke joinery. Also record decisions that cross trades. A socket behind a lit mirror involves joinery, electrical work and wall finish; settling it late can mean drilling finished tiles.
Do not wait for the weekly meeting if a work stage is stalled. Send the question that day with two or three photographs, a marked plan and the date by which an answer is needed. “Do whatever you think is best” rarely protects the programme or budget. Ask for an explicit choice or a clear instruction approving the proposed solution.
Before quotes are requested, a finish schedule removes many foreseeable queries. The clarification log then deals with exceptions, clashes and decisions that only emerge when existing walls and services are opened up.

Every answer should point to the document that it confirms or changes: a quotation item, drawing, manufacturer sheet, approved sample or email. This stops a decision from being mistaken for authorisation of additional work.
If an answer changes price, quantity, timing or a contracted solution, ask for a change proposal before instructing the work. Record the amount, effect on the programme and acceptance. This matters particularly where the choice seems minor, such as changing a finish, moving a radiator or adding recessed lighting.
Changes to an approved design can require their own procedure. Lisbon City Council explains that certain changes during construction are subject to an amendment to the licence or prior communication, depending on the case; others may be dealt with as in-work changes within the applicable limits. Check the municipal guidance on changes during construction before assuming that a site decision is only an internal matter.
The client should decide matters of use, appearance and budget. The designer answers issues that depend on the design and coordination. The contractor should flag construction clashes, access constraints, sequencing and material concerns. The supplier confirms product characteristics, lead times and installation requirements. One person — usually the work coordinator — closes the loop: sends the decision, identifies who has been informed and checks that it reached the relevant work stage.
Set one simple rule: an urgent verbal instruction works only as a temporary alert; by the end of the day it goes into the log with written confirmation. This is not about distrust. It prevents one team working from an old message while another has received a changed instruction by phone.
Where work is subject to prior communication, Lisbon City Council states that design documents, contractor documents and, where applicable, technical management and supervision documents form part of the submission. Review the requirements for prior communication for building works; a clarification log must follow those documents, never contradict them.
Set aside ten minutes at the start of each meeting to review open items only. Order them by the date on which they will block a task, rather than by room. A question about an appliance width may be more urgent than five decorative choices if kitchen units are due the following week.
Also check that the contractor holds the appropriate activity qualification through IMPIC channels. The log cannot repair a poorly prepared appointment, but it gives the team a shared basis for delivering what was actually agreed.
For decisions with a financial effect, link every item to the approved quotation version and the renovation contingency budget. When comparing a change with the quotation, confirm whether it includes supply, labour, delivery lead time and any effect on the work sequence. The guide to renovation quotes in late 2026 helps separate these elements before a seemingly simple decision becomes an untracked cost.
Key takeaways
If you are preparing a renovation in Lisbon, speak to Obra Lisboa about organising scope, decisions and coordination before work begins. A clear starting point reduces uncertainty once trades are already on site.
Sources and further reading
Editorial image; it does not depict an Obra Lisboa project.
Privacidade e controlo
Usamos cookies essenciais para o funcionamento do site. Com a sua autorização, podemos também medir a utilização e os resultados dos anúncios. A medição de publicidade com a OpenAI usa referências técnicas, sem enviar nome, email, telefone ou mensagem do pedido. Pode aceitar, rejeitar ou gerir cada categoria. Consulte a Política de Privacidade e a Política de Cookies.
Necessários para segurança, navegação e memorização da sua escolha.
Ajuda a medir utilização e desempenho sem enviar dados de contacto.
Permite medir campanhas, incluindo anúncios no ChatGPT. Com a OpenAI, a medição usa referências técnicas para associar pedidos aos anúncios, sem enviar nome, email, telefone ou mensagem. É opcional e pode ser desativada a qualquer momento.