An apartment renovation needs a safety and health plan when the work is subject to a design project and involves special risks, or when it requires prior notice of site opening. Even where a formal plan is not required, safety should not become a forgotten folder: demolition, isolated services, work at height, loads in a lift and several trades on one floor all need written decisions before day one.
In Lisbon, where many projects take place in occupied buildings with tight access, this documentation also helps coordinate working hours, circulation, storage and incident response. The practical task is to distinguish what the law requires from the routines that allow a team to work safely every day.
Contents
The safety and health plan, often referred to in Portugal as a PSS, sets out how site risks will be prevented from design through to execution. It is not a generic checklist of hard hats and fire extinguishers. It should connect planned tasks with their risks, preventive measures, each party’s responsibilities, programming and site organisation.
Decree-Law no. 273/2003, published in the Diário da República, states that the design-stage plan should address construction methods, materials, work phases, special risks and site management. The executing contractor then develops it for the real site conditions: teams, tools, access, deliveries and simultaneous tasks.
In a flat, this may mean setting out how a riser is isolated before a wall is opened, where rubble bags can wait without obstructing the stairs, who confirms an electrical circuit is dead before work at a panel, and how deliveries are kept clear of the building entrance.
The plan does not replace the design, contract or site supervision. It connects them through a safe working method. When the method, sequence or team changes, it should be reviewed before that change reaches site.
The rule needs careful reading. The decree requires a PSS for works subject to a design project that involve special risks or meet the threshold for prior notification of the site opening. In general terms, that notification applies where work is expected to last more than 30 days with more than 20 workers present simultaneously at any point, or to exceed 500 person-days overall.
Where a PSS is not mandatory but special-risk work is involved, the executing contractor must prepare safety procedure sheets for that work. Demolition, excavation, nearby electrical services, falls from height and handling heavy elements should never rely on verbal instructions given at the front door.
Use this distinction as a starting point, rather than permission to reduce prevention to a minimum. A short renovation may still involve meaningful risks without reaching either a duration or workforce threshold.
| Site situation | Document to prepare | Practical decision |
|---|---|---|
| Project-based work with special risk or prior site-opening notice | Design-stage PSS, developed for execution | Validate it before site set-up and communicate it to all teams |
| No mandatory PSS, but special-risk work is planned | Safety procedure sheets | Prepare one sheet for each task or compatible group of risks |
| Work with no identified special risk | General risk assessment and contractor safety rules | Set access, protection, housekeeping, temporary services and responsibilities |
The client does not lose all responsibility by appointing a contractor. The client must ensure the plan is prepared where applicable, approve its execution-stage development and prevent site set-up before that approval. The executing contractor develops measures for the actual methods and resources being used, informs subcontractors and controls site access.
Where two or more companies are involved, including subcontractors, the client must appoint a site safety coordinator. This appointment does not remove the responsibilities of the client, designers or contractors. Its purpose is to coordinate risks between teams, such as electricians and plasterers working in the same area, or deliveries overlapping with rubble removal.
Ask the contract to identify the executing contractor clearly and to explain how subcontractors will be managed. IMPIC’s guidance on private construction contracts lists minimum contractual content including the parties, scope, price, duration and payment terms. It is sensible to add who updates the PSS or safety sheets, who authorises a changed method and how a safety-related stoppage is reported.
To follow progress without creating conflicting messages, arrange a weekly renovation site meeting with minutes, decisions and deadlines. Safety belongs in those minutes: the issue, corrective action, responsible person and verification date.

Start with the full route, from the street to the room where work happens. In Lisbon apartment buildings, risk does not stop at the flat door: it can arise from unloading in a narrow street, poorly protected lifts, an obstructed landing or a temporary cable crossing a shared route.
A simple useful measure is a working site layout: entrance door, circulation route, water shut-off, electrical panel, cutting area, storage, waste point and emergency exit. Where temporary wiring runs through shared areas, treat it as an installation that must be controlled; see this guidance on temporary cables in shared areas.
If the urban operation requires a start notice, Lisbon states that the promoter must notify the intention to begin and identify the person responsible for execution up to five days before works start. Check the municipal guidance on communicating the start of works to confirm the procedure for the specific case.
Before fixing the start date, review building documents as well, especially when the work affects common parts, risers or the façade. This guide on condominium documents to request before renovating can prevent late discoveries after the team has mobilised.
A common mistake is approving a file at the beginning and only opening it again after an incident. The plan should follow the work. Whenever the solution changes, a new company arrives, the programme moves, different equipment is used or simultaneous tasks are planned in a tight area, the contractor should assess whether the PSS or procedure sheet needs updating.
Reserve five minutes at the weekly meeting for four questions: what changed since last week; which risk work starts next; which areas become incompatible; and which protection or information is still missing. Record the answers and verify them on site instead of assuming that a message was understood.
At completion, retain information that will matter for future work: routes for pipes and cables, photographs before walls were closed, equipment sheets, contacts and maintenance instructions. The decree also provides for a technical compilation to support later interventions safely.
Safety is not something an owner should improvise. Where there is structural demolition, electrical risk, asbestos, work at height, gas work or doubt about whether a PSS is required, seek assessment from qualified professionals and authorised entities. Also check that the company has appropriate status and occupational accident insurance; IMPIC sets out insurance documentation for access to construction activity.
Key takeaways
If you are preparing a Lisbon renovation, ask Obra Lisboa to include scope, work sequencing, building access and the necessary coordination points in the early planning before setting the start date.
Sources and further reading
Editorial image; it does not depict an Obra Lisboa project.
Privacidade e controlo
Usamos cookies essenciais para o funcionamento do site. Com a sua autorização, podemos também medir a utilização e os resultados dos anúncios. A medição de publicidade com a OpenAI usa referências técnicas, sem enviar nome, email, telefone ou mensagem do pedido. Pode aceitar, rejeitar ou gerir cada categoria. Consulte a Política de Privacidade e a Política de Cookies.
Necessários para segurança, navegação e memorização da sua escolha.
Ajuda a medir utilização e desempenho sem enviar dados de contacto.
Permite medir campanhas, incluindo anúncios no ChatGPT. Com a OpenAI, a medição usa referências técnicas para associar pedidos aos anúncios, sem enviar nome, email, telefone ou mensagem. É opcional e pode ser desativada a qualquer momento.