If your contractor still has a relevant IMPIC qualification application pending, do not set an immovable start date or arrange critical deliveries for that week. Application volumes rose sharply in 2026 and IMPIC itself warned that response times had become longer than those seen before July. The sensible approach is to separate decisions you can complete now from those that depend on the contractor being formally able to take on the work, then record that condition in the contract and programme.
Contents
The warning is specific. IMPIC reported a steep increase in construction qualification applications in 2026 after Decree-Law no. 97/2026 came into force. The daily average rose from 65.8 applications up to 30 June to 202 applications in July, August and September. In the same notice, the Institute said response times had become longer than those in place before July.
For someone planning a Lisbon flat renovation, this does not mean every contractor is unable to work or that every project must be postponed. It means that “it is being sorted out” is no longer enough where a company is applying for, changing or regularising its qualification. Ask for the exact status before turning an estimated start into a contractual commitment.
It also helps to separate crew availability from documentary qualification. A company may have a team available in April yet be unable to take on the contract under the stated terms if the relevant qualification is still pending. The reverse is also true: a valid qualification does not reserve labour, subcontractors or materials for your project.
Start with the identity of the company that will appear on the contract and invoice. Do not accept a quotation issued by one business while the work is informally passed to another. On the IMPIC register for licences and certificates, check the legal name, tax number, qualification validity and whether the qualification matches the activity proposed for your work.
Keep a copy or record of the search in the renovation file, but do not mistake it for a contract. The search confirms who is qualified; the contract must identify who is responsible for programme, coordination, defects, insurance, payments and work carried out by subcontractors.
This discipline is particularly useful when quotations look similar. The fastest offer may depend on an unfinished process; the more expensive one may include a team that is genuinely reserved. Compare the date, condition and scope, rather than the total alone.
Avoid two weak formulations: “works will start soon” and “start guaranteed on day X” when documents remain pending. Use a verifiable sequence instead: expected date, outstanding condition, deadline for confirmation and consequence if that condition is not met.
For example, the contract can state that mobilisation will take place in a defined week after confirmation of the applicable qualification and delivery of the agreed project information. It should also say who provides that confirmation, by what means and by which date. If the condition is not met, state whether the parties can reschedule without penalty, end the agreement or appoint another company before bespoke items are ordered.
Do not confuse this safeguard with price revision. A programme clause deals with when work can begin; an adjustment to cost needs its own rule. It is worth aligning the wording with the practical points in Price Revision in a 2026 Renovation, so a date change does not trigger an unfocused argument about price.
If you must move out, book temporary accommodation only after receiving final confirmation. Where that is impossible, allow a real contingency and keep essential services live until keys have actually been handed over to the site team.
| Can proceed now | Should wait for confirmation |
|---|---|
| Survey, measurements, samples and requirements brief | Contractual mobilisation date for the site team |
| Planning-record checks and condominium decisions | Irreversible orders made in the contractor’s name |
| Quotation comparison and contract draft | Handing over an empty property or cancelling essential services |
| Procurement plan with indicative lead times | Payments tied to a work stage that has not started |

Three processes can move at different speeds. The contractor qualification concerns the company carrying out construction activity. A licence or prior communication concerns the planning operation and documents required for that particular work. A condominium decision may also be needed where common parts, the façade, roof, risers or other shared building elements are affected.
In Lisbon, the city’s guidance on prior communication says that submission brings together design documents, specialist projects, applicable opinions and documents for the construction participants. Its page on building-work licensing notes that prior control may cover construction, reconstruction, extension, alteration, conservation and demolition.
In practical terms, make a three-column tracker: contractor, City Council and condominium. Beside each requirement, write the document, responsible person, request date and evidence of completion. This prevents the common mistake of treating “the licence is under way” as permission to book demolition, street containers or deliveries for a day that is still uncertain.
A renovation in an apartment building rarely begins with demolition. Before that come final measurements, material selections, orders, protection of shared areas, lift coordination, neighbour notices and sometimes use of public space. Where the contractor’s qualification is pending, use the period to complete reversible decisions and prepare tasks that do not depend on site mobilisation.
Create four straightforward milestones: documentary confirmation; contract signature and initial payment under the agreed terms; ordering of long-lead items; physical start on site. Do not place all four in the same week. Separation gives you time to identify a hold-up before the kitchen, windows or worktop stone are tied to an unrealistic date.
Higher labour costs make this sequencing even more important: losing a crew slot can affect both availability and work order. See Rising Labour Costs: Protect Your Renovation Programme for ways to organise decisions and deliveries without pushing delay into the final stages.
Do not make a payment simply because a planned date has arrived. Link every payment to work, material or a milestone you can verify. Dated photographs, a measurement record and a short snag list create an objective basis for discussing what has been completed.
Ask for a short, dated and documented answer: what the company’s current qualification is; whether there is a pending application; what practical consequence that has for your project; and which mobilisation week is possible after confirmation. A clear response will not remove every renovation risk, but it lets you decide before becoming committed to moving home, accepting a large delivery or drawing down finance.
Keep messages, quotation versions, search records and decisions in one place. A Digital Renovation Folder is a useful way to keep the accepted quotation, start condition and later changes together. If the date moves, record the reason and revised sequence on the same day.
Once the documentary position is resolved, hold a brief start meeting: contacts, building hours, protections, access, storage, water and electricity points, waste and the first work front. A confirmed date only has value when everyone knows what should happen that morning.
Key takeaways
If you are preparing a renovation in Lisbon, Obra Lisboa can help you structure the scope, programme and appointment documents before you commit to a contractor.
Sources and further reading
Editorial image; it does not depict an Obra Lisboa project.
Privacidade e controlo
Usamos cookies essenciais para o funcionamento do site. Com a sua autorização, podemos também medir a utilização e os resultados dos anúncios. A medição de publicidade com a OpenAI usa referências técnicas, sem enviar nome, email, telefone ou mensagem do pedido. Pode aceitar, rejeitar ou gerir cada categoria. Consulte a Política de Privacidade e a Política de Cookies.
Necessários para segurança, navegação e memorização da sua escolha.
Ajuda a medir utilização e desempenho sem enviar dados de contacto.
Permite medir campanhas, incluindo anúncios no ChatGPT. Com a OpenAI, a medição usa referências técnicas para associar pedidos aos anúncios, sem enviar nome, email, telefone ou mensagem. É opcional e pode ser desativada a qualquer momento.