In a renovation, there should always be one company or person clearly accountable to the client, even when demolition, plumbing, electrics, plasterboard, joinery and painting are carried out by different teams. The key is not to ban subcontracting: it may be used on private works unless the contract restricts it. The key is to know who coordinates the trades, who confirms a change and who takes responsibility when one trade leaves a problem for the next. Set this out before appointment, in writing, with operational contacts.
Contents
A renovation company may carry out part of the work with its own staff and use subcontractors for specialist trades. The IMPIC guidance on contracts and subcontracting states that, on a private project, subcontracting may cover all of the contract work if the contract does not say otherwise. That does not turn the homeowner into the coordinator of separate teams.
Ask the quotation to identify:
A familiar example is an electrician cutting chases, a plumber changing a route and the finishes team then finding that a wall has not been made ready. Without defined coordination, every trade may say the task belongs to the previous one. With one accountable lead, the issue goes on a list, receives an owner and gets a resolution date.
“Full renovation of a two-bedroom flat” is not enough. The contract should connect the price to documents that make the agreed work recognisable: an itemised quotation, approved drawings, finishes schedule, exclusions and programme. IMPIC notes that private-work contracts above the legal threshold must be in writing and must include the parties, qualifications, scope, price, completion period and payment terms.
Add a practical subcontracting clause. It does not need to name every painter, but it should state that the appointed company retains coordination, remains responsible for the contracted work and gives prior notice of any replacement that changes sequencing, access, safety or the expected standard.
It is also sensible to set out:
This provides a working base for a renovation kick-off meeting, where documents become tasks for the first week on site.
Before appointing anyone, check the company taking responsibility for the project, rather than only the trading name on the quotation. The IMPIC consultation portal provides access to company records, licences, certificates, registrations and recently cancelled statuses. For a private project, the company responsible for execution must hold a licence class that covers the total value of the works, according to IMPIC guidance on the responsible contractor’s qualification.
Keep the legal company name, tax number, address, site contact, qualification reference and accepted quotation version in the project file. Where the work needs specific technicians or procedures, ask for them to be identified in the work plan and establish who contacts you when a design issue arises.
Do not treat the main-company check as an automatic guarantee for every site decision. Qualification is a necessary control; day-to-day quality still relies on clear drawings, decision records and confirmation before walls, ceilings or floors are closed.
Avoid two recurring problems: appointing a “team” without an identified contracting entity, and allowing each trade to invoice you separately when the quotation was offered as a single main contract. Both make it harder to establish who must resolve an interface defect.

Use a short, shared and current spreadsheet. Each line should cover a decision, delivery or work front that can hold up another. There is no need to turn a domestic renovation into a burdensome process; the point is to stop information disappearing.
For each line, record:
When a decision changes, do not delete the previous one. Mark it as superseded, date it and link the new instruction. This is particularly useful in kitchens and bathrooms, where a small change can affect joinery, water points, electrics, finishes and delivery dates.
For work in an apartment building, coordinate access and deliveries as well. Our guide to a three-week Lisbon renovation plan shows how to connect decisions, teams and materials without leaving one trade waiting for another.
Not every change is a problem. Some reveal a concealed condition: a wall out of square, old pipework, a slab that blocks the planned route or a discontinued product. The mistake is solving it verbally and discovering the consequences at the end.
When a team proposes a change, ask for a note answering four questions: what was found; what solution is proposed; which work, materials or drawings are affected; and what the effect is on cost and programme. The coordinator should check whether the solution affects another trade before asking for your approval.
Do not accept “we will sort it out later”. If work must continue to prevent a leak, electrical risk or damage to the property, record the urgency and request immediate written confirmation afterwards. For purely aesthetic changes, stop the affected work front until there is a decision. Losing a morning is preferable to ordering incompatible tiles or joinery.
For works requiring municipal communication, confirm the applicable procedure and the identification of the person in charge of execution through Lisbon City Council’s work-commencement guidance.
In the final weeks, coordination should not disappear simply because the teams look finished. Inspect room by room and organise outstanding items by responsible party, with a photo, location and target date. Separate workmanship defects, ordinary touch-ups, missing materials and operating questions.
Before the final payment, check at least the following:
A well-coordinated project does not rely on having one team on site. It relies on the client knowing who decides, who carries out the work and where each commitment is recorded. If you are preparing a renovation in Lisbon, Obra Lisboa can help structure the scope, programme and coordination between trades before appointment.
Key takeaways
Preparing to request renovation quotations? Ask Obra Lisboa for an initial discussion about the project scope and coordination needed, bringing your drawings, preliminary quotation and the decisions already confirmed.
Sources and further reading
Editorial image; it does not depict an Obra Lisboa project.
Privacidade e controlo
Usamos cookies essenciais para o funcionamento do site. Com a sua autorização, podemos também medir a utilização e os resultados dos anúncios. A medição de publicidade com a OpenAI usa referências técnicas, sem enviar nome, email, telefone ou mensagem do pedido. Pode aceitar, rejeitar ou gerir cada categoria. Consulte a Política de Privacidade e a Política de Cookies.
Necessários para segurança, navegação e memorização da sua escolha.
Ajuda a medir utilização e desempenho sem enviar dados de contacto.
Permite medir campanhas, incluindo anúncios no ChatGPT. Com a OpenAI, a medição usa referências técnicas para associar pedidos aos anúncios, sem enviar nome, email, telefone ou mensagem. É opcional e pode ser desativada a qualquer momento.